Planned Maintenance

60 Day Maintenance Schedule

 

 

Roofing Replacement Has Been Completed

Pressure Washing

Includes Stairwells and Handrails

Building Serviced

Building 11
Building 10
Building 9
Building 8
Building 7
Building 6
Building 5
Building 4
Building 3
Building 2
Building 1

Planned Date

08/01/2024
08/08/2024
08/15/2024
08/22/2024
08/29/2024
09/05/2024
09/12/2024
09/19/2024
09/26/2024
10/03/2024
10/10/2024

Trash Pickup

Trash Pick up

Monday, Thursday, Saturday

Pest Control

Pest Control Applications

Pest Control is applied Quarterly

     October 11, January 11, April 11, July 11

Paint Buildings (2 perYear)

Building Paintings

     Building 5            October/November

Property Landscaping

Weekly Mowing, blowing, edging, trimming

Thursday

Contact the Dawn management office to report landscaping issues at 409-740-3488

Monthly Gate Maintenance

Arrival Date

On or about the 17th of the month.  Gates may be temporarily open from time to time to check, lubricate and test ALL Dawn gates: 61st Street Gates (2), Seawall Exit Gate and Walk Ins

Swimming Pool (both ) and SPA Maintenance

Chemicals and other Needs

Daily before 9 AM or by mass email notice
May open earlier as conditions permit

Contact the Dawn management office for actual opening times at 409-740-3488